Skip to content

Building Regulations

Demolition is dealt with under the Building Act 19841. Generally, it requires six weeks prior notice to be given to the Local Authority's building control before demolition begins.

The Local Authority's building control department may decide to issue a notice within six weeks of receipt of the notification to specify conditions that need to be met which may include precautions to protect adjoining properties and the public.

Demolition work must also comply with the Construction (Design and Management) Regulations 20152 and a health and safety plan produced by the principal contractor.

Building Regulations relating to site preparation and resistance to contaminants and moisture will need to be met once the preparation work starts on the site.

Please contact the Local Authority's building control department3 for further advice.


Find a Trade Professional

Use our partner directories from CIAT, FMB or RTPI to find an chartered architectural technologist, builder or planning consultant to help with your project or development.

Find a professional


Useful links

Make an application Studio Charrette planning consultancy calculator
    1. http://www.legislation.gov.uk/ukpga/1984/55/contents
    2. http://www.legislation.gov.uk/uksi/2015/51/contents/made
    3. https://planningportal.pp.tqinfra.co.uk/applications/building-control-applications/building-control/find-your-LABC

    The Planning Portal is delivered by PortalPlanQuest Limited which is a joint venture between TerraQuest Solutions Limited and the Ministry of Housing, Communities & Local Government (MHCLG). All content © 2024 Planning Portal.

    The Planning Portal is delivered by PortalPlanQuest Limited which is a joint venture between TerraQuest Solutions Limited and the Ministry of Housing, Communities & Local Government (MHCLG). All content © 2024 Planning Portal.